Planned Work Status
Â
KPI Name | Planned Work Status |
---|---|
Definition | It shows count of the issues having a due date which are planned to be completed until today and how many of these issues have actually been completed. It also depicts the delay in completing the planned issues in terms of days. |
Calculation Logic | Planned - Show only the ones with due date Actual Delay is calculated between due Date & completed Date of issue. Potential Delay is calculated between due Date & Predicted Completed Date. |
Filters | Filter by Issue type Filter by Priority |
Columns in Overlay Screen |
|
Configuration | Â |
Processor Fields | NA |
Mandatory fields | NA |
© 2022 Publicis Sapient. All rights reserved.