Sprint Predictability

Overview

Overview

Definition (Hover Text)

Measures the percentage the iteration velocity against the average velocity of last 3 iteration.

Source Tools

Jira, Azure

Graph type

Line

Filters

-

Hover Format on KPI

Sprint Name: <<Percentage Value>>

Fields on Overlay

Sprint Name

Story ID

Issue Description

Size

Business Logic

Calculation Formula

It is calculated as

sprint velocity of the targeted sprint/average sprint velocity of previous 3 sprints

Trend

 

Maturity Levels

NA

Instance level thresholds

 

Global Configurations (Field Mapping)

Processor Fields

NA

Mandatory fields

Project Settings

  1. Navigate to Project Settings: Start by going to the Project Settings in your application.

  2. Access the Mapping Section: Within Project Settings, find and click on the Mapping option.

  3. Mandatory Field: In the Mapping section, you’ll find the Mandatory Field. This is where you’ll configure the necessary global mapping fields.

  4. Configure the Fields:

    1. Story Points Custom Field: Specify the field in Jira that is used for Story Points.

image-20240703-134423.png
  • Estimation Criteria: Choose your preferred estimation criteria. You can select either Story Points or Original Estimation.

image-20240703-140124.png
  • Sprint Name: Provide the custom field that is linked with the Sprint.

image-20240703-140346.png

How to Validate KPI

Suggested ways of working

 

Sample JQLs

NA

Benefits of KPI

How does the KPI help

  1. Helping teams forecast how much work they can complete in a sprint.

  2. Allowing for better planning and allocation of resources.

  3. Ensuring more accurate estimations of Sprint timelines and delivery dates.