Anything that is marked RED, is part of Backlog
KPI Name / Definition | Representation | Tool | Maturity Levels | KPI Calculation | On Hover | Remarks | |||||||||
Issue Countmeasures the overall work taken in a sprint | Line Graph
| Agile Project Management
| No Maturity Trend | It is calculated as No. of stories tagged to a Sprint | Sprint Name: <<Value>> |
| |||||||||
Sprint Velocitymeasures the rate at which a team can deliver every Sprint. Since a stable velocity helps in forecasting, the KPI also measures the last 5 sprints average velocity and plots it along with the sprint velocity | Line Graph
| Agile Project Management
| No Maturity Trend | SPRINT VELOCITY calculated as Sum of story points of all stories completed within a Sprint Last 5 sprints | Sprint Name: <<Value>> |
| |||||||||
Commitment Reliabilitymeasures the percentage work completed at the end of a sprint in comparison to the total work in the sprint | Line Graph
| Agile Project Management
| M1 - <40% M2 - 40-60% M3 - 60-75% M4 - 75% - 90% , M5 - > 90% | It is calculated No. of issues or Size of issues completed/No. of issues or Size of issues committed
| Sprint Name: <<Percentage Value>> Delivered: <<Count/Size>> Committed: <<Count/Size>> |
| |||||||||
Sprint PredictabilityMeasures the percentage the iteration velocity against the average velocity of last 3 iteration. | Line Graph
| Agile Project Management
| M5 - 95% -105% | It is calculated as sprint velocity of the targeted sprint/average sprint velocity of previous 3 sprints | Sprint Name: <<Percentage Value>> | ||||||||||
Sprint Capacity Utilizationdepicts explains the maximum amount of time a team can commit within sprinteffectiveness of sprint planning and sprint execution. | Line Graph + Column chart
| Agile Project Management
| M1: <20% M2: 20-40%, M3: 40-60%, M4: 60-80%, M5: >80% | SPRINT CAPACITY UTILIZATION This KPI is calculated based on 2 parametersEstimated Hours3 parameters and showcases 2 views Available Capacity: It explains depicts the total hours required to complete Sprint backlogavailable for the Sprint . The capacity is can defined in KnowHOW. Refer to Capacity Management Estimated Hours: Sum of the estimation of all issues taken in the sprint is considered as Estimated hours Logged WorkHours: The amount of time team has logged within a Sprint. It is derived as sum of all logged work against issues tagged to a Sprint in Jira | Sprint Name: <<Value>> |
| |||||||||
Scope ChurnScope churn explains the change in the scope of sprint since the start of iteration | Line Graph
| Agile Project Management
| M1: >50% M2: 30-50% M3: 20-30% M4: 10-20% M5: <10% | Scope Churn = (Stories added + Stories removed) / Count of Stories in Initial Commitment at the time of Sprint start | Sprint Name: <<Value>> |
Average Resolution time | |||||||||
measures average time taken to complete an issue that could be a story or bug etcPlanning Accuracymeasures if the team is planning iterations based on either capacity or the historical velocity. | Line Graph
| Agile Project Management
| M1 : => 10 days M2 : 8-10 days M3 : 5-8 days M4 : 3-5 days, M5 : <= 3 days | Sum of resolution times of all issues completed in the Sprint/No. of issues completed within a sprint
*If the KPI data is not available for last 5 sprints, the Maturity level will not be shown | Overall filter option is configurable at the instance level | Number of Check-ins & Merge requestshelps in measuring the transparency as well the how well the tasks have been broken down. | M1: 0-2 M2: 2-4 M3: 4-8 M4: 8-16 M5: >16 | NUMBER OF MERGE REQUESTS when looked at along with commits highlights the efficiency of the review process
| Mean time to mergemeasures the efficiency of the code review process in a a team | M1 : > 48 Hours M2 : 16 - 48 Hours M3 : 8 - 16 Hours M4 : 4-8 Hours, M5 : <4 Hours |
| Date Range: <<Hours>M5 - 95% -105% | Based on Average Velocity Planned work in SP/Average Velocity Based on Planned Capacity Planned work/Available Capacity | Sprint Average Velocity/Planned Capacity - 50 SP or100 Hrs Planned work - 50 SP or100 Hrs | Under configuration, user gets to select through a radio button
|
Code Build Timemeasures the time a job takes to build the code. | Line Graph
| Agile Project Management
| M1 : > 45 min M2 : 30-45 mins M3 : 15-30 min M4 : 5-15 min, M5 : <5 min |
| Date Range: <<min>> Commitment Reliabilitymeasures the percentage work completed at the end of a sprint in comparison to the total work in the sprint Line Graph
| Agile Project Management
| M1 - <40% M2 - 40-60% M3 - 60-75% M4 - 75% - 90% , M5 - > 90% | It is calculated No. of issues or Size of issues completed/No. of issues or Size of issues committed
| Sprint Name: <<Percentage Value>> Delivered: <<Count/Size>> Committed: <<Count/Size>> |