KPI Name

Unplanned Work Status

Definition (info)

It shows count of the issues which do not have a due date. It also shows the completed count amongst the unplanned issues.

Calculation Logic

Overall Unplanned - Show the issues which doesn’t have due date

Completed - Show amongst the ones which are not having due date and completed.

Filters

Filter by Issue type

Filter by Priority

Columns in Overlay Screen

  1. Issue ID

  2. Issue Description

  3. Issue Status

  4. Issue Type

  5. Size (Story Point/Hours)

  6. Original Estimate

  7. Due Date

  8. Actual Completion date

  9. Delay

  10. Predicted Completion Date

  11. Potential Delay

  12. Assignee

Configuration

Processor Fields

NA

Mandatory fields

NA