Start date & End date of the Iteration
Days left in the Iteration
Capacity of the Iteration (In Hours)
Capacity is defined for each Iteration under the Capacity tab under Settings
Capacity can be defined for the complete team
Capacity can be defined for each individual and the tools sums it for the team
If the capacity is not defined, it is seen as 'N/A'
Predicted completion date : Predicted completion date (PCD) is calculated for an issue after factoring in all the work (issues) assigned to an individual, the issue with earliest due date and each issues corresponding remaining estimate. Assumption is that 'In Progress' issues are being worked upon so first the PCD by adding remaining estimate to todays date and similarity the PCD's are calculated for other In Progress and Open issues.
...